A5086 Resurfacing & Civils Works

Get in touch

Image
Civil Engineering / Surfacing & Cold Milling

  • ClientCumberland Council

  • Value£1,200,000

  • DurationNovember 2024 - December 2024

"This was a large scheme on a busy thoroughfare leading up to Christmas, so it was important to avoid unnecessary disruption to commuters and local residents. To receive lots of positive feedback was great!"
Daryl Kelly - Operations Manager North

The brief

With DSD Construction acting as Primary Contractor to Cumberland Council, the scope of work included resurfacing and civils works on a section of the A5086 at Cleator Moor – a busy road connecting West Cumbria to the rest of the county and to the A66 trunk road across Northern England.

Our scope of work on this scheme included:

  • Approximately 5,000m2 of replacement footways and 2,000m kerbing.

  • Set up of the construction compound and site welfare for all site operatives.

  • Approximately 300 items of ironwork removed and replaced.

  • Planed out and relaid the carriageway to depths of 100mm using 50mm AC20 HDM Hardstone Binder, AC32 HDM Base and 35/14 HRA.

  • Renewed footways using type 1 subbase, AC20 Binder and AC6 asphalt.

  • Excavated and installed ducting for new broadband and electricity services.

  • Installed new road signs.

Key quantities:

  • AC20 HDM Hardstone Binder: 1,800 t
  • AC32 HDM Base: 60 t
  • HRA 68 PSV: 1,500 t

Challenges & successes

The works were progressed in six phases through Cleator Main Street on day and night shifts, with road closures, traffic management and stop & go measures utilised at different stages of the works to minimise road user disruption.

Due to the works being carried out in a residential area within 1 metre of houses, pre-planning was required to ensure public safety. Letter drops to local residents, pre-start meetings with Cumberland Council and local councillors, and walk-in meetings for the public to ask questions directly to DSD Construction and Cumberland Council all made the residents and public feel involved with the scheme.

Due to the Christmas holidays, we could not close the road after the 6th December. Due to our excellent planning, we completed all road closure works 4 days earlier than programmed and then continued work under traffic light and stop & go control to allow the carriageway to be reopened to the public.

Outputs & Benefits

Positive feedback: We received a lot of positive feedback regarding this scheme from members of the public and our client.

Maintained access: The road was closed to the public, but access was maintained throughout the works to residents, school buses, and emergency services each shift through the use of a temporary running lane.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.
Find Out More

Image
DSD Construction Services