A59 junction reconstruction, Green Hammerton

Get in touch

Image
Surfacing & Cold Milling

  • ClientExcel / Avant

  • Value£260,000

  • DurationAugust 2022 - September 2022

The original and additional scope were completed on time during a very restricted working window.

The project scope

A new housing development required a more suitable road junction with the main A59 which involved the relocation of the existing junction by 500m, construction of a new link road section and tie in of the new junction to the existing A59.

Due to the importance of the main A59 Harrogate to York trunk road, the work was carried out under full night- time road closure.

Our scope of work included:

  • Surveys and setting out
  •  Traffic Management
  • Surfacing of the new housing development access road
  •  Surfacing of the new junction with Base, Binder, and Hot Rolled Asphalt with Pre-Coated Chippings
  • Planing out 270m of the existing A59 to create the tie-in to the new junction
  • Resurfacing of the existing A59 to tie-in to the new junction
  • Surfacing of 880m2 of footpath
  • White lining
  • Replacement of studs

Key quantities:

  • AC32 Base: 200 t
  • Binder with hard stone: 200 t
  • 35/14 HRA with 68 PSV pre coated chips: 420 t

Challenges & successes

Due to the importance of the A59 Harrogate to York trunk road and due to other project delays, we were allocated 2 nights to complete all the works. Additionally, during the works, we were requested to lay an additional 72t of AC6 asphalt for the footpaths. To meet this deadline, we deployed multiple gangs and 3 pavers simultaneously – our mini, midi and large pavers.

The site was located adjacent to housing, and we worked with the residents to minimise noise during the night. We planned our work to complete the noisiest operations before 11pm (mainly planing operations) and briefed our workforce to work as quietly as possible (e.g. no shouting, no loud radios, no horn beeping etc).


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.
Find Out More

Image
DSD Construction Services