Bridge 30 deck refurbishment, Sellafield, Cumbria

Get in touch

Image
Civil Engineering

  • ClientMorgan Sindall

  • Value£200,000

  • DurationJuly 2022 - August 2022

We safely completed the refurbishment of the bridge deck whilst maintaining pedestrian access during a summer heatwave.

The project scope

The scheme involved the removal of Bridge 30 deck surface and footpaths to carry our structural repairs and waterproofing before reinstatement of the asphalt surface on a critical vehicle / pedestrian bridge across the river Calder on the Sellafield nuclear site. Our scope of work included:

  • Surveys and setting out
  • Traffic and pedestrian management
  • Construction of a temporary pedestrian walkway
  • Planing out of the existing bridge deck road surface and footpaths
  • Repairs to the bridge deck structure using Metoset concrete repair resin
  • Silicone waterproofing of the bridge deck structure using our specialist sub-contractor Volker Laser
  • Installation of geotextile layers to the bridge deck
  • Reconstruction of kerbing and footpaths
  • Reinstatement of base, binder and wearing road and footpath asphalt surface
  • White lining of the road surface

Key quantities:

  • Planing & resurfacing: 140 t
  • Kerbing: 40 m
  • Silicone waterproofing: 300 m²

Challenges & successes

The bridge is one of only 3 bridges across the River Calder on the Sellafield nuclear site which are required for site operational, construction and workforce traffic. Although vehicle diversions were implemented during the works, pedestrian access had to be maintained across bridge 30 as much as possible to provide workforce access to the operational facilities. This was facilitated by constructing a temporary pedestrian walkway across the bridge which had to remain open as much as possible.

The project was delivered during a summer heatwave with temperatures of more than 32 degrees Celsius. To work within the specification of the waterproofing silicone, we had to work at night when the temperature dropped to acceptable levels.

Due to the security classification of the Sellafield nuclear site, our subcontractors were required to have security clearance. Due to the short term and urgent need of the works, we collaborated with the Sellafield Ltd security department to allow our subcontractor to work on site under special security arrangements.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.