Bridge 2 deck refurbishment, Sellafield, Cumbria

Get in touch

Image
Civil Engineering

  • ClientMorgan Sindall & Cumberland Council

  • Value£175,000

  • DurationOctober 2022

We safely completed the refurbishment of the bridge deck whilst maintaining access to the Sellafield nuclear site and railway station.

The project scope

The scheme involved the removal of Bridge 2 deck surface and footpaths to carry out structural repairs and waterproofing before reinstatement of the asphalt surface on a critical vehicle / pedestrian bridge outside the Sellafield nuclear site main gate for our clients Morgan Sindall and Cumbria County Council. This was a critical project due to its location being immediately next to the main Sellafield site access gate and Sellafield railway station – both of which require 24/7 access. Our scope of work included:

  • Surveys and setting out.
  • Traffic and pedestrian management.
  • Construction of a temporary pedestrian walkway.
  • Planing out of the existing bridge deck road surface and footpaths.
  • Excavation beneath bridge deck.
  • Repairs to the bridge deck structure using Metoset concrete repair resin.
  • Silicone waterproofing of the bridge deck structure using our specialist sub-contractor Volker Laser.
  • Installation of geotextile layers to the bridge deck.
  • Reconstruction of kerbing and footpaths.
  • Reinstatement of base, binder and wearing road and footpath asphalt surface.
  • White lining of the road surface.

Key quantities:

  • Planing & resurfacing: t
  • Kerbing: 20 m
  • Silicone waterproofing: 250 m²

Challenges & successes

The bridge provides a single access route to one of the Sellafield site’s main access gates and to the Sellafield railway station, which are in constant use by many of the site’s 10,000 staff and vehicles.

To maintain constant access, we coordinated our work with Sellafield Ltd (site owner/operator), Morgan Sindall, Network Rail and Cumbria County Council. To minimise disruption, we worked flexibly around key site access requirements and worked 12-hour day and night shifts to complete the work as quickly as possible.

To maintain traffic flow, we installed traffic management and vehicle segregation to allow one lane to remain open and avoided working at peak traffic commuter times.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.