Cargo Fleet Lane A66 roundabout reconfiguration

Get in touch

Image
Civil Engineering / Surfacing & Cold Milling

  • ClientA E Yates

  • Value£1,600,000

  • DurationNovember 2019 - June 2020

Efficient construction of the new A66 roundabout with minimal disruption to pedestrians and road users.

The project scope

Reconfiguration of a major roundabout on the A66 dual carraigeway trunk road to provide a through road across the centre of the roundabout. The roundabout remained in traffic and pedestrian use at all times and the project involved:

  • Full survey and marking out.
  • Laying of new ducting for electric, telecoms and pedestrian crossing services.
  • Construction of new gullies and drainage systems in the kerbs.
  • Construction of temporary footways to maintain pedestrian safety during construction.
  • Construction of new permanent footways.
  • Construction of new dual carriageway through the centre of a previously landscaped roundabout.
  • Installation of street furniture and signage.
  • Landscaping, including weed spraying, stone picking, top soiling and grass seeding.

Key quantities:

  • Road planing: 15,500 m²
  • Excavation: 2,567 m3
  • Carriageway: 2,970 m²

Challenges & successes

This section of the A66 is extremely busy with high levels of traffic and pedestrian footfall. We were not allowed to reduce the number of traffic lanes or close any of the footways during the daytime. We overcame this constraint by working night shift so that we could reduce traffic to a single lane and by constructing the works in smaller sections.

All removed topsoil, kerbs, flags, blacktop and concrete was crushed, screened and reused in the works, saving material, disposal and transport cost whilst also significantly reducing the carbon footprint of the project.

During the COVID-19 pandemic, we took advantage of the quiet roads and low traffic flow to reschedule our work to deliver the project on time despite the additional social distancing and logistics constraints.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.
Find Out More

Image
DSD Construction Services