- ClientRingway
- Value£800,000
- DurationNovember 2019 - June 2020
Efficient footpath construction around existing trees whilst maintaining pedestrian access at all times.
The project scope
Reconfiguration of a major roundabout on the A66 dual carraigeway trunk road to provide a through road across the centre of the roundabout. The roundabout remained in traffic and pedestrian use at all times and the project involved:
- Full survey and marking out.
- Laying of new ducting for electric, telecoms and pedestrian crossing services.
- Construction of new gullies and drainage systems in the kerbs.
- Construction of temporary footways to maintain pedestrian safety during construction.
- Construction of new permanent footways.
- Construction of new dual carriageway through the centre of a previously landscaped roundabout.
- Installation of street furniture and signage.
- Landscaping, including weed spraying, stone picking, top soiling and grass seeding.
Key quantities:
- Footway surfacing: 19,000 m
- Pedestrian crossings: 20
- Traffic light crossings: 2
Challenges & successes
Tree roots were encountered at frequent intervals during footpath excavation. To overcome this, small roots were cut out, the path level was raised to avoid large tree roots and the path was diverted around some trees, requiring changing the width to maintain clearances.
Due to the proximity to the busy adjacent road, it was essesntial to maintain footpath access at all times for pedestrians. To overcome this, the construction work was split into smaller sections and small plant was used (1.5Te and 2.5Te machines). The project schedule was changed to accommodate continual pedestrian access, smaller construction areas and small capacity machines. This approach worked very well and we have been praised by our clients and the public for keeping the footpath open.