Ellesmere Port Sutton Way footpath expansion

Get in touch

Image
Civil Engineering / Surfacing & Cold Milling

  • ClientRingway

  • Value£800,000

  • DurationNovember 2019 - June 2020

Efficient footpath construction around existing trees whilst maintaining pedestrian access at all times.

The project scope

Reconfiguration of a major roundabout on the A66 dual carraigeway trunk road to provide a through road across the centre of the roundabout. The roundabout remained in traffic and pedestrian use at all times and the project involved:

  • Full survey and marking out.
  • Laying of new ducting for electric, telecoms and pedestrian crossing services.
  • Construction of new gullies and drainage systems in the kerbs.
  • Construction of temporary footways to maintain pedestrian safety during construction.
  • Construction of new permanent footways.
  • Construction of new dual carriageway through the centre of a previously landscaped roundabout.
  • Installation of street furniture and signage.
  • Landscaping, including weed spraying, stone picking, top soiling and grass seeding.

Key quantities:

  • Footway surfacing: 19,000 m
  • Pedestrian crossings: 20
  • Traffic light crossings: 2

Challenges & successes

Tree roots were encountered at frequent intervals during footpath excavation. To overcome this, small roots were cut out, the path level was raised to avoid large tree roots and the path was diverted around some trees, requiring changing the width to maintain clearances.

Due to the proximity to the busy adjacent road, it was essesntial to maintain footpath access at all times for pedestrians. To overcome this, the construction work was split into smaller sections and small plant was used (1.5Te and 2.5Te machines). The project schedule was changed to accommodate continual pedestrian access, smaller construction areas and small capacity machines. This approach worked very well and we have been praised by our clients and the public for keeping the footpath open.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.
Find Out More

Image
DSD Construction Services