Promenade highways improvements, Bowness on Windermere

Get in touch

Image
Civil Engineering

  • ClientCumberland Council

  • Value£450,000

  • DurationFebruary 2022 - May 2022

The project was completed 2 weeks early in the busiest town in the Lake District over the Easter holiday break.

The project scope

The scheme involved the refurbishment, reconfiguration, and enhanced access to the promenade area in the busy tourist town of Bowness on Windermere. The scope of work included:

  • Design using our partner Capita
  • Surveys and setting out of the site
  • Removal of old paving and bedding sand
  • Installation of slab concrete
  • Installation of new Westmorland green slate flag paving
  • Installation of specialist Westmorland and Cumberland slate setts
  • Installation of tactile crossings
  • Construction of new public seating
  • Installation of bollards and rock features
  • Construction of wing walls and installation of access gates
  • Installation of topsoil, grass seed and chipped bark landscaping

Key quantities:

  • Public seating units: 8
  • Rock features: 36
  • Bollards: 55

Challenges & successes

The project was carried out in the busiest tourist area of the Lake District National Park during the spring public holiday period. This required us to segregate the construction areas from the public using Heras fencing and avoid working at peak times – including weekends and public holidays.

The project was located adjacent to Windermere Lake Cruises (WLC) – the main tourist attraction in the town. We worked closely with WLC to ensure we did not disrupt their business by liaising daily, working around their peak times, and avoiding holiday periods. We also made 50% of our working areas available to WLC for the 3-week Easter holiday period so that they could maximise their business revenue. Our Site agent was commended by WLC for the way we managed the project. Despite the Easter holiday period constraints, we completed the project 2 weeks early.

One of the constraints of the project was that we could not disrupt 2-way traffic flow past the construction site. Instead using traffic light controls, we installed Rhino barriers to maintain our sideways safety zone whilst still allowing 2-way traffic to pass.

https://dsdconstruction.com/wp-content/uploads/2022/08/DSD_Windermere-Prom_May22.mov


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.
Find Out More