Redmoss to Clayhills Civils Reinstatement & Resurfacing

Get in touch

Image
Civil Engineering / Surfacing & Cold Milling

  • ClientBalfour Beatty

  • Value£750,000

  • DurationAugust 2025 - May 2026

"This project was an excellent example of our team working seamlessly to deliver a high‑quality outcome across multiple key locations. The way the team approached and delivered the works showcases our ability to deliver complex civil engineering schemes within high‑profile environments."
Craig Whyte - Pre Construction Manager

The brief

This complex project involved two phases of work across 12 locations between Redmoss and Clayhills in Aberdeen, focused on removing temporary works and reinstating previous excavation areas on an existing utilities renewal scheme.

Phase 1 scope of work included:

  • Removal of temporary works installations..

  • Backfilling of excavations to the required formation levels.

  • Carriageway reinstatement including AC32, AC20 and HRA surface courses.

  • Footpath and associated kerb reinstatement.

Phase 2 scope of work included:

  • Excavation of two additional trial pits.

  • Installation of temporary works to allow specialist access to electrical ducting for repair works.

  • Backfilling and reinstatement after completion of duct repairs, followed by final resurfacing, white lining and full site clearance.

Key quantities:

  • Hardcore: 3,000 t
  • Asphalt Materials: 350 t
  • High-Impact Locations: 12

Challenges & successes

With Phase 1 falling over the Christmas period, we successfully completed all scheduled works ahead of the holiday break. This enabled the client to reopen the area to traffic as normal and prevented any significant impact on the local community.

The works extended across 12 high‑impact locations, each with its own operational constraints and stakeholder sensitivities. Through effective planning, sequencing, and clear communication, the team was able to deliver the works safely and efficiently across all areas while minimising disruption.

A complex network of underground services was present throughout the site, requiring detailed surveys and carefully controlled excavation strategies to ensure safe progress. Despite these challenges, the team completed all works without any utility strikes or unplanned outages.

Outputs & Benefits

Health & Safety: There were zero reportable incidents or accidents throughout the works.

Snag-Free Completion: Upon completion, the sites were inspected with the client, and no snags were identified.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.
Find Out More