Sellafield Pile 1 chimney tower crane base construction

Get in touch

Image
Civil Engineering

  • ClientDoosan Babcock

  • Value£2,500,000

  • DurationDecember 2016 - December 2017

Construction of the new tower crane base in a highly congested and regulated nuclear environment.

The project scope

Installation of the first phase of demolition equipment for dismantling of the iconic 70-year-old Pile 1 chimney at Sellafield. The project involved:

  • Ground investigation works and the handling/removal of contaminated spoil
  • Installation and testing of temporary working platforms for the piling rig and 300 Te mobile crane
  • Assisting the piling contractor with the installation of the 16m steel cased piles for the tower crane base
  • Construction of the RC crane base (85m3) for the erection of the 150m high tower crane, including all associated formwork/falsework temporary works, reinforcement and concrete testing
  • Construction of a new storage and handling facility for the contaminated waste concrete sections generated during demolition, which included a bespoke retractable tent system, change room facilities and perimeter security fencing
  • Construction of the new RC gantry crane base used for the movement, manipulation and loading of the contaminated concrete sections
  • Installation of new surface water and foul water drainage systems

Key quantities:

  • Excavation: 200 m3
  • RC concrete: 420 m3
  • Reinforcement: 75 t

Challenges & successes

The work was carried out in a high radiation / contamination area which required additional workforce training and working procedures to be implemented. This caused some delays to the schedule, but we worked in collaboration with our client and the piling contractor to recover the schedule.

The work was carried out in a high security area of the site with access restrictions. This required us to manage labour, plant and material logistics in and out of the site in close collaboration with our client and the security department. This involved accurate forecasting and planning by providing a 3 week logistics look ahead plan – continually detailing all labour, plant and material access requirements.

We discovered a significant amount of uncharted buried cables, pipework and underground structures during excavation. To overcome this, we used Vacuum Excavation which accelerated the works, mitigated the schedule delays and reduced the safety hazard of hand digging in this area.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield