South Lakeland rail crossing refurbishment

Get in touch

Image
Civil Engineering / Surfacing & Cold Milling

  • ClientNeary Rail

  • Value£50,000

  • DurationMarch 2019 - June 2019

Our flexible approach and night shift working ensured that the rail line was reopened on time.

The project scope

Resurfacing of new rail crossings as part of the rail crossing replacement project at Sandscale, Barrow in Furness. We removed and reinstated the road after the rail crossing installation, which included:

  • Full survey and marking out
  • Cold milling of the existing carriageway.
  • Carriageway surfacing.
  • Installation of white lining
  • Installation of carriageway studs.
  • Use of Hotbox to maintain asphalt temperature

Key quantities:

  • Cold milling: 650 m²
  • Surfacing: 650 m²
  • Asphalt: 150 t

Challenges & successes

The line had to be closed to carry out the crossing replacement, meaning we had to work flexibly within the line closure / possession schedule. We worked at night within the agreed possession slots whilst always being able to reopen the line at short notice in the event of an emergency. Our working methods were planned so that we always worked from the rail line to the outside of the crossing to allow short notice reopening.

Due to the pre allocated possession slots and the requirement to finish work and reopen the line on time after each possession, we provided standby plant and equipment for use in the event of breakdowns.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.
Find Out More

Image
DSD Construction Services