Water supply diversion, Calder Hall decommissioning project, Sellafield, Cumbria

Get in touch

Image
Civil Engineering

  • ClientAltrad Babcock

  • Value£60,000

  • DurationApril 2023

Extensive stakeholder engagement and planning resulted in a successful project delivered on time.

The project scope

This project involved the diversion of a critical water supply at the Sellafield nuclear site in Cumbria. The water supply diversion was required to allow additional isolation points and water supply feeds to be installed to facilitate ongoing decommissioning of the Calder Hall nuclear power station. The project included several months of planning and stakeholder engagement prior to site access to ensure water supplies to existing operational facilities were not interrupted. Our scope of work included:

  • Extensive stakeholder engagement, planning and work pack development.

  • Excavation to 2.2m depth to access the water supply pipework.

  • Installation of temporary sheet piling, and trench supports.

  • Removal of existing pipework.

  • Installation of new pipework and divertor valves.

  • Pressure testing.

  • Removal of temporary works.

  • Backfill and resurfacing.

Challenges & successes

The project had to be completed without interrupting the water supplies to the operational facilities at Sellafield. This required us to plan the work 8 months in advance, engage with several dozen stakeholder groups including the Sellafield Utilities department, and carry out the pipework removal, reinstallation, and testing during the weekend.

The pipework modification was carried out in a Confined Space which necessitated the use of air powered tools rather than internal combustion engine to eliminate the risks associated with carbon monoxide.

The successful completion of this project enabled our client and the site owner to continue with the Calder Hall decommissioning programme at Sellafield.


Image
Latest Case Studies
A66 Great Broughton to Fitz Roundabout Resurfacing
Surfacing & Cold Milling
Resurfacing 4.6km of the A66 between Great Broughton and Fitz Roundabout, Cockermouth – covering eastbound and westbound carriageways along the main trunk road providing access to West Cumbria.
Find Out More
B5292 Lorton Street Resurfacing, Recycling & Civils
Civil Engineering / Surfacing & Cold Milling
With DSD Construction acting as Principal Contractor to Cumberland Council, this scheme involved planing and resurfacing of the B5292 carriageway at Lorton Street, Cockermouth using recycled materials to avoid hazardous waste disposal of tar bound material.
Find Out More
B2 Reinforced Concrete Prop Installation, Sellafield
Civil Engineering
With DSD Construction acting as subcontractor to Altrad Babcock, this scheme involved the installation of reinforced concrete props in a nuclear facility to allow installation of a large roller shutter door to facilitate future decommissioning works.
Find Out More

Image
DSD Construction Services