- ClientTSP Projects Ltd
- Value£80,000
- DurationMarch 2019 - November 2019
Gainsborough and Woodlesford station platforms and extensions successfully resurfaced in restricted access locations.
The project scope
Resurfacing of the existing platforms and surfacing of the new platform extensions at Gainsborough and Woodlesford stations. Work was carried out at night when site possession was available and included:
- Full survey and marking out
- Removal of existing platform surface
- Preparation of sub base
- Resurfacing of existing platforms
- Surfacing of new platform extensions.
- Material hand barrowed into site due to restricted access
- Material hand laid in difficult access areas
Key quantities:
- Platform resurfacing: 1,200 m²
- Asphalt: 300 t
Challenges & successes
Access to the workface was restricted meaning we couldn’t deliver materials using wagons. To overcome this we used small plant (e.g. 1Te Dumpers and hand barrows) to transport the material to the final workface.
The station remained in use by the public throughout the works. In order to maintain passenger and train safety we established robust pedestrian management and segregation arrangements and worked around the train schedules. We worked closely with the train planners and paused work 10 minutes before trains were due and restarted 10 minutes after trains departed.